Case Study #6 | Water & Wastewater Plant Deep Lift

Case Study #6 | Water & Wastewater Plant Deep Lift

The Client Water & Wastewater Treatment Plant in Greensville Alabama Project Requirements To lift three 3,500 lb. pumps in a 26 ft. deep by 25 ft. wide pit. The Challenge Previously, a large crane had to be called in to lift the pumps. This expensive solution for...
Case Study #5 | Rental House Gantry Crane

Case Study #5 | Rental House Gantry Crane

The Client A rental company Project Requirements The client needed to move huge air conditioning units on the roof of a large building. The Challenge Getting the appropriate lifting equipment to handle a rooftop job, without blowing the budget. The Solution By using...
Case Study #4 | Wastewater Facility Space Issue

Case Study #4 | Wastewater Facility Space Issue

The Client Wastewater Facility Project Requirements To move a 10,000 lb. membrane. The Challenge The space in which this membrane was to be moved was extremely tight. The Solution An eme PRO 11000R Gantry Crane could do the job! Because of the tight space,...